Production Order - link to related subcontracting documents

BUSINESS VALUE / REQUIREMENT

With standard functionalities it is difficult to navigate to subcontracting documents related to a production order.

Add buttons to show related documents directly from production order cards. On prod. orders, provide link to related subcontracting documents (Purchase Orders and Purchase Receipts).

Production Order - Link to related Subcontraction Documents

For Handling Subcontract Manufacturing see https://docs.microsoft.com/en-us/dynamics365/business-central/production-how-to-subcontract-manufacturing.

The Subcontraction Management is planned by a Work Center, which is linked to a Vendor. Then this Work Center is used for a Routing Operation. If you calculate a Production Order with this Routing the Work Center / Operation is transfered to the Production Order. If you Release these Production Order you are able to cretae Purchase Orders for the Subcontractor. If you are Invoiceing the Purchase Order the Production Order are booked with Capacitiy Ledger Entries for this Work Cneter with the Value of the Purchase Invoice.

Master Date for Work Center and Routing

Work Center, Open Work Centers Lists

1.PNG

Create Work Center with a Subcontractor No.

2.PNG

Routing, Open Routings Lists

3.PNG

Create Routing with the above Work Center

4.PNG

Link the above Routing with an item. Fill field "Routing No." on Replenishment FastTab on Item Card with the No. from Routing above.

5.PNG

Production Order

Create Production Order where the above item is used. Change the Status to Released (or create directly Relesed Production Order).

Only Production Orders with Status Released can be Purchased as Subcontractors.

Open Released Production Orders Lines.

6.PNG

Fill all mandotory fields and refresh production order.

7.PNG

8.PNG

9.PNG

Subcontracting Worksheet

To Create Purchase Orders from Released Procution Orders the Subcontracting Worksheets are used. You can calculate the Subcontracting Operations.

Open Subcontracting Worksheet Lists and Calculate Subcontracts

10.PNG

->the above Production Order with the Routing Line for the above Work Center has to appear

11.PNG

Carry Out Action Message for the Subcontracting worksheet line with our above Production Order

12.PNG

13.PNG

-> a new purchase order is created

Purchase Order

Open Purchase Orders Lists and open the new purchase order

14.PNG

In the Purchase Order Line, "Line"-Section, the new button "Production Order" appears and when the user clicks the button the related Production Order will open.

15.PNG

Production Order

In the Released Production Order, "Line"-Section, the new button "Purchase Order" appears with two sub buttons for "Order" and "Receipts".

16.PNG